Question: Estimating project cash flows is generally the most important, but also the most difficult, step in the capital budgeting process. Methodology, such as the use of NPV versus IRR, is important, but less so than obtaining a reasonably accurate estimate of projects’ cash flows.

True
False

Answer: a. True

 

Question: 7. Any cash flows that can be classified as incremental to a particular project—i.e., results directly from the decision to undertake the project—should be reflected in the capital budgeting analysis.

True
False

Answer: a. True

 

Question: Assume a project has normal cash flows. All else equal, which of the following statements is CORRECT?

Answer Options:
a. A project’s IRR increases as the WACC declines.
b. A project’s NPV increases as the WACC declines.
c. A project’s MIRR is unaffected by changes in the WACC.
d. A project’s regular payback increases as the WACC declines.
e. A project’s discounted payback increases as the WACC declines.

Answer: b

 

Question: Variance is a measure of the variability of returns, and since it involves squaring the deviation of each actual return from the expected return, it is always larger than its square root, the standard deviation.

a. True
b. False

Answer:

 

Question: An individual stock’s diversifiable risk, which is measured by its beta, can be lowered by adding more stocks to the portfolio in which the stock is held.

a. True
b. False

Answer:

 

Question: Which of the following statements is CORRECT?
a. If the maturity risk premium were zero and interest rates were expected to decrease in the future, then the yield curve for U.S. Treasury securities would, other things held constant, have an upward slope.
b. Liquidity premiums are generally higher on Treasury than corporate bonds.
c. The maturity premiums embedded in the interest rates on U.S. Treasury securities are due primarily to the fact that the probability of default is higher on long-term bonds than on short-term bonds.
d. Default risk premiums are generally lower on corporate than on Treasury bonds.
e. Reinvestment risk is lower, other things held constant, on long-term than on short-term bonds.

Answer Options:
a. False
b. False
c. False
d. False
e. True

Answer: e. True

 

Question: The difference between a stock and a bond is which of the following?

Stock pays interest and a bond pays dividends.
Stock pays dividends and bonds pay interest.
Banks receive special dividends.
There is no difference between stock and a bond.

Answer: Stock pays dividends and bonds pay interest.

 

Question: Because of differences in the expected returns on different investments, the standard deviation is not always an adequate measure of risk. However, the coefficient of variation adjusts for differences in expected returns and thus allows investors to make better comparisons of investments’ stand-alone risk.

a. True
b. False

Answer:

 

Question: Which of the following statements is CORRECT?

Answer Options:
a. The MIRR and NPV decision criteria can never conflict.
b. The IRR method can never be subject to the multiple IRR problem, while the MIRR method can be.
c. One reason some people prefer the MIRR to the regular IRR is that the MIRR is based on a generally more reasonable reinvestment rate assumption.
d. The higher the WACC, the shorter the discounted payback period.
e. The MIRR method assumes that cash flows are reinvested at the crossover rate.

Answer: c

 

Question: Projects C and D are mutually exclusive and have normal cash flows. Project C has a higher NPV if the WACC is less than 12%, whereas Project D has a higher NPV if the WACC exceeds 12%. Which of the following statements is CORRECT?

Answer Options:
a. Project D probably has a higher IRR.
b. Project D is probably larger in scale than Project C.
c. Project C probably has a faster payback.
d. Project C probably has a higher IRR.
e. The crossover rate between the two projects is below 12%.

Answer: a

 

Question: Which of the following statements is CORRECT?

Answer Options:
a. The internal rate of return method (IRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
b. The payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
c. The discounted payback method is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
d. The net present value method (NPV) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.
e. The modified internal rate of return method (MIRR) is generally regarded by academics as being the best single method for evaluating capital budgeting projects.

Answer: d

 

Question: The slope of the SML is determined by investors’ aversion to risk. The greater the average investor’s risk aversion, the steeper the SML.
a. True
b. False

Answer: True

 

Question: Under the CAPM, the required rate of return on a firm’s common stock is determined only by the firm’s market risk. If its market risk is known, and if that risk is expected to remain constant, then analysts have all the information they need to calculate the firm’s required rate of return.

a. True
b. False

Answer:

 

Question: A stock’s beta is more relevant as a measure of risk to an investor who holds only one stock than to an investor who holds a well-diversified portfolio.

a. True
b. False

Answer: