Question: The internal rate of return is that discount rate that equates the present value of the cash outflows (or costs) with the present value of the cash inflows.

Answer Choices:
a. True
b. False

Answer: a. True

Question: Which of the following statements is CORRECT?

Answer Choices:
a. If a project has “normal” cash flows, then its IRR must be positive.
b. If a project has “normal” cash flows, then its MIRR must be positive.
c. If a project has “normal” cash flows, then it will have exactly two real IRRs.
d. The definition of “normal” cash flows is that the cash flow stream has one or more negative cash flows followed by a stream of positive cash flows and then one negative cash flow at the end of the project’s life.
e. If a project has “normal” cash flows, then it can have only one real IRR, whereas a project with “nonnormal” cash flows might have more than one real IRR.

Answer: e. If a project has “normal” cash flows, then it can have only one real IRR, whereas a project with “nonnormal” cash flows might have more than one real IRR.

Question: The primary reason that the NPV method is conceptually superior to the IRR method for evaluating mutually exclusive investments is that multiple IRRs may exist, and when that happens, we don’t know which IRR is relevant.

Answer Choices:
a. True
b. False

Answer: b. False

Question: Which of the following statements is CORRECT?

Answer Choices:
a. For a project to have more than one IRR, then both IRRs must be greater than the WACC.
b. If two projects are mutually exclusive, then they are likely to have multiple IRRs.
c. If a project is independent, then it cannot have multiple IRRs.
d. Multiple IRRs can only occur if the signs of the cash flows change more than once.
e. If a project has two IRRs, then the smaller one is the one that is most relevant, and it should be accepted and relied upon.

Answer: d. Multiple IRRs can only occur if the signs of the cash flows change more than once.

Question: Which of the following statements is CORRECT?

Answer Choices:
a. One advantage of the NPV over the IRR is that NPV takes account of cash flows over a project’s full life whereas MIRR does not.
b. One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the WACC, whereas IRR assumes that cash flows are reinvested at the IRR. The NPV assumption is generally more appropriate.
c. One advantage of the MIRR over the NPV method is that NPV discounts cash flows whereas the MIRR is based on undiscounted cash flows.
d. Since cash flows under the IRR and MIRR are both discounted at the same rate (the WACC), these two methods always rank mutually exclusive projects in the same order.
e. None of the above is true.

Answer: One advantage of the NPV over the IRR is that NPV assumes that cash flows will be reinvested at the WACC, whereas IRR assumes that cash flows are reinvested at the IRR. The NPV assumption is generally more appropriate.

Question: Four of the following statements are truly disadvantages of the regular payback method, but one is not a disadvantage of this method. Which one is NOT a disadvantage of the payback method?

Answer Choices:
a. Lacks an objective, market-determined benchmark for making decisions.
b. Ignores cash flows beyond the payback period.
c. Does not directly account for the time value of money.
d. Does not provide any indication regarding a project’s liquidity or risk.
e. Does not take account of differences in size among projects.

Answer: d. Does not provide any indication regarding a project’s liquidity or risk.

Question: In theory, capital budgeting decisions should depend solely on forecasted cash flows and the opportunity cost of capital. The decision criterion should not be affected by managers’ tastes, choice of accounting method, or the profitability of other independent projects.

Answer Choices:
a. True
b. False

Answer: a. True

Question: Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows.

Answer Choices:
a. If Project A has a higher IRR than Project B, then Project A must have the lower NPV.
b. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.

Answer: b. If Project A has a higher IRR than Project B, then Project A must also have a higher NPV.

Question: Although it is extremely difficult to make accurate forecasts of the revenues that a project will generate, projects’ initial outlays and subsequent costs can be forecasted with great accuracy. This is especially true for large product development projects.

Answer Choices:
a. True
b. False

Answer: False

Question: Which of the following statements is CORRECT?

Answer Choices:
a. Projects with “normal” cash flows can have only one real IRR.
b. Projects with “normal” cash flows can have two or more real IRRs.
c. Projects with “normal” cash flows must have two changes in the sign of the cash flows, e.g., from negative to positive to negative. If there are more than two sign changes, then the cash flow stream is “nonnormal.”
d. The “multiple IRR problem” can arise if a project’s cash flows are “normal.”
e. Projects with “nonnormal” cash flows are almost never encountered in the real world.

Answer: a. Projects with “normal” cash flows can have only one real IRR.

Question: When evaluating mutually exclusive projects, the modified IRR (MIRR) always leads to the same capital budgeting decisions as the NPV method, regardless of the relative lives or sizes of the projects being evaluated.

Answer Choices:
a. True
b. False

Answer: b. False