A general contractor is managing a construction project that will add a new conference room to an existing office building. The project was documented in a fixed-price contract. The contract includes a damages clause imposing a late completion penalty if the conference room is not ready for use by the contracted deadline. The project has fallen behind schedule. Therefore, to avoid the contractual penalty, the project team will use fast-tracking to compress the duration of the remaining schedule. Which change management phase does this scenario describe?
Answer Choices:
Answer: Managing the change
What should the team do to plan the quality of this scope upgrade?
Answer Choices:
Answer: Identify and apply the relevant ANSI standards.
Which process would increase confidence that the crashing effort will not reduce the project’s quality?
Answer Choices:
Answer: Quality assurance
Which two actions should the project team perform to prepare for the potential scope change?
Answer Choices:
Answer:
When does a negative cost variance (CV) occur in earned value management?
Answer Choices:
Answer: When the actual cost is more than the earned value
What is the documentation that provides assurance that products or services have been delivered on time and as ordered?
Answer Choices:
Answer: Vendor invoice
What are two purposes of project closeout?
Answer Choices:
Answer:
The customer of a project has validated that scope has been completed for a beta test. Which closure phase does this describe?
Answer Choices:
Answer: Deliverable completion
A project is nearing completion, and the entire project team is meeting. During the meeting, the team discusses a part of the project that went particularly well, and the person responsible for that task describes how they were able to exceed expectations. Another discussion summarizes a part of the project that was over budget and how the team could have prevented the cost overrun. Which project closeout process is taking place in this meeting?
Answer Choices:
Answer: Lessons learned review
A firm begins its strategic business initiative of developing a new business model that will allow the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm initiates a business management project. Which objective of project management is directly related to the tailored service?
Answer Choices:
Answer: Stakeholder satisfaction
When does a negative cost variance (CV) occur in earned value management?
Answer Choices:
Answer: When the actual cost is more than the earned value
What is the documentation that provides assurance that products or services have been delivered on time and as ordered?
Answer Choices:
Answer: Vendor invoice
What are two purposes of project closeout?
Answer Choices:
Answer:
What is one of the five levels of project management maturity?
Answer Choices:
Answer: Managed process
Which scenario describes a project?
Answer Choices:
Answer: A sporting goods store installs a new point-of-sale system.
A firm with many ongoing projects deploys an organizational structure where the project manager defines what needs to be accomplished and establishes the project plan, schedule, and budget. Additionally, the functional manager determines how the project will be accomplished by assigning personnel and executes plans in accordance with the standards set by the project manager. Which type of organizational structure is this firm using?
Answer Choices:
Answer: Balanced matrix organizational structure
Which advantage does the projectized organizational structure provide for a firm with multiple projects?
Answer Choices:
Answer: A skilled project team can support successive projects of the same type.
An organization expects to use a project management office (PMO) to support multiple projects that will be implemented within a functional organizational structure. Which benefit will this organization gain?
Answer Choices:
Answer: Project team members will maintain access to current technologies and skill sets.
Regardless of the organizational structure used to manage a project, an organization elects to use a project management office (PMO). Which three benefits will this organization gain?
Answer Choices:
Answer: Lessons learned will be applied to other projects. Best practices will be identified from project reviews. Organizational policies will be available in a central repository.