Answer: a
Question: The option to abandon a project is a real option, but a call option on a stock is not a real option. a. True b. False
Answer: a
Question: Which of the following statements is CORRECT? a. In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project’s cash flows will lead to an upward bias in the NPV. b. In a capital budgeting analysis where part of the funds used to finance the project would be raised as debt, failure to include interest expense as a cost when determining the project’s cash flows will lead to a downward bias in the NPV. c. The existence of any type of “externality” will reduce the calculated NPV versus the NPV that would exist without the externality. d. If one of the assets to be used by a potential project is already owned by the firm, and if that asset could be sold or leased to another firm if the new project were not undertaken, then the net proceeds that could be obtained should be charged as a cost to the project under consideration. e. If one of the assets to be used by a potential project is already owned by the firm but is not being used, then any costs associated with that asset is a sunk cost and should be ignored.
Answer: d
Question: The NPV and IRR methods, when used to evaluate two equally risky but mutually exclusive projects, will lead to different accept/reject decisions and thus capital budgets if the cost of capital at which the projects’ NPV profiles cross is greater than the crossover rate.
Answer Options:
a. True
b. False
Answer: b. False
Question: Although the replacement chain approach is appealing for dealing with mutually exclusive projects that have different lives, it is not used in practice because not projects meet the assumptions the method requires. a. True b. False
Answer: b
Question: A firm is considering a new project whose risk is greater than the risk of the firm’s average project, based on all methods for assessing risk. In evaluating this project, it would be reasonable for management to do which of the following? a. Increase the estimated IRR of the project to reflect its greater risk. b. Increase the estimated NPV of the project to reflect its greater risk. c. Reject the project, since its acceptance would increase the firm’s risk. d. Ignore the risk differential if the project would amount to only a small fraction of the firm’s total assets. e. Increase the cost of capital used to evaluate the project to reflect its higher-than-average risk.
Answer: e
Question: The two methods discussed in the text for dealing with unequal project lives are (1) the replacement chain approach and (2) the present value approach. a. True b. False
Answer: b
Question: Which of the following statements is CORRECT? a. The regular payback method recognizes all cash flows over a project’s life. b. The discounted payback method recognizes all cash flows over a project’s life, and it also adjusts these cash flows to account for the time value of money. c. The regular payback method was, years ago, widely used, but virtually no companies even calculate the payback today. d. The regular payback is useful as an indicator of a project’s liquidity because it gives managers an idea of how long it will take to recover the funds invested in a project. e. The regular payback does not consider cash flows beyond the payback year, but the discounted payback overcomes this defect.
Answer: d
Question: Which of the following statements is CORRECT? a. Using accelerated depreciation rather than straight line would normally have no effect on a project’s total projected cash flows but it would affect the timing of the cash flows and thus the NPV. b. Under current laws and regulations, corporations must use the same depreciation method for all assets whose lives are 5 years or longer. c. Corporations must use the same depreciation method (e.g., straight line or accelerated) for stockholder reporting and tax purposes. d. Since depreciation is not a cash expense, it has no effect on cash flows and thus no effect on capital budgeting decisions. e. Under accelerated depreciation, higher depreciation charges occur in the early years, and this reduces the early cash flows and thus lowers a project’s projected NPV.
Answer: a
Question: The optimal capital budget is the size of the capital budget where the rate of return on the marginal project is equal to the marginal cost of capital. a. True b. False
Answer: a
Question: Estimating project cash flows is generally the most important, but also the most difficult, step in the capital budgeting process. Methodology, such as the use of NPV versus IRR, is important, but less so than obtaining a reasonably accurate estimate of projects’ cash flows. a. True b. False
Answer: a
Question: In theory, capital budgeting decisions should depend solely on forecasted cash flows and the opportunity cost of capital. The decision criterion should not be affected by managers’ tastes, choice of accounting method, or the profitability of other independent projects.
Answer Options:
a. True
b. False
Answer: a. True
Question: Real options are most valuable when the underlying source of risk—such as uncertainty about unit sales, or the sales price, or input costs—is very low. a. True b. False
Answer: b
Question: If you were evaluating two mutually exclusive projects for a firm with a zero cost of capital, the payback method and NPV method would always lead to the same decision on which project to undertake.
Answer Options:
a. True
b. False
Answer: b. False
Question: Projects C and D are mutually exclusive and have normal cash flows. Project C has a higher NPV if the WACC is less than 12%, whereas Project D has a higher NPV if the WACC exceeds 12%. Which of the following statements is CORRECT? a. Project D probably has a higher IRR. b. Project D is probably larger in scale than Project C. c. Project C probably has a faster payback. d. Project C probably has a higher IRR. e. The crossover rate between the two projects is below 12%.
Answer: d